Sample Package · Westside Medical Office Bldg · Mode A Full Bid
← Back Book a Call
SAMPLE PACKAGE — Anonymized project for demonstration. This is actual Vernier Mode A output format. Your projects produce the same structure calibrated to your trade, market, and margin targets.
Vernier AI · Mode A · Full Bid Package
Westside Medical Office Building
Complete Electrical Systems · New Construction · 24,000 SF · Olympia, WA 98501
A
Full Bid
Owner
Cascadia Health Properties LLC
General Contractor
Summit Construction Co.
Drawings Reference
100% CDs — Addendum 4 incl.
Bid Date
April 30, 2026 · 2:00 PM PT
Prevailing Wage
Yes — WA L&I rates included
Design-Build Element
Yes — EV charging design assist
Vernier Run Date
April 15, 2026 · 14:32 PT
Tokens Used
1,142,800
Self-Perform Advantage
+$38,400
Cost savings vs. a GC who subs your scope entirely. Includes direct labor efficiency, no sub markup, and single-point accountability on coordination. This number belongs in your cover letter.
Design-Build Scope
EV Charging
Owner has not finalized EV charging layout. Included design-assist service in Platinum tier — 24 Level 2 station rough-in based on current IEV-100 series drawings. Confirm with owner before Gold/Silver award.
Tiered Bid Proposals Click tier to expand
⭐ Platinum
Turnkey Zero-Risk
Complete scope · Owner-managed risk · Extended warranty
$512,400
Complete electrical systems for Westside Medical Office Building including all work shown on Drawings E-100 through E-412 and as specified in Division 26. Platinum tier includes extended warranty, owner-directed change buffer, dedicated project manager with direct owner contact, design-assist services for EV charging layout, and owner dashboard access for real-time project status. All risk items quantified in the risk register are carried within this price — owner has no exposure to cost escalation on items noted.
  • Extended 3-year workmanship warranty on all installed systems
  • Dedicated PM — direct owner cell and email, 2-hour response guarantee
  • $24,000 owner-directed change buffer included — unused portion credited at project close
  • EV charging design-assist service: layout optimization for 24 Level 2 stations, load study, utility coordination
  • All permits, inspection fees, and utility interconnect fees included
  • Weekly owner progress reports with photo documentation
  • Commissioning and owner training on all installed control systems
  • All items in the risk register carried within Platinum price — no change orders on listed items
⬡ Gold — Primary Bid
Full-Scope Managed
Complete scope · Standard industry terms · Target margin
$481,200
Complete electrical systems per 100% Construction Documents and Addendum 4. Full scope as documented including main service entrance, power distribution, lighting and controls, fire alarm, nurse call rough-in, site lighting, EV charging rough-in (24 circuits per current IEV-100 drawings), and all associated permits and inspections. Standard 1-year workmanship warranty. WA L&I prevailing wage rates effective April 2026 included.
  • Main electrical service: 2,000A 480/277V 3Ø switchboard, utility company coordination included
  • Power distribution: 7 panelboards (3 × 480V, 4 × 208/120V), all feeders and branch circuits
  • Lighting systems: interior LED per schedule, Lutron dimming and occupancy sensors, daylight harvest zones
  • Emergency lighting: 90-minute battery backup per NFPA 101 occupancy requirements
  • Fire alarm: addressable system, Notifier FACP per FA-001 riser diagram
  • Nurse call: Rauland Responder 5 rough-in per NC-100 series drawings (equipment by owner)
  • Site lighting: 14 LED pole fixtures, building-mounted security lighting per E-300 series
  • EV charging: 24 circuits, Level 2 capable, panel capacity per IEV-100 (EVSE by owner)
  • All permits and inspections; WA prevailing wage certified payroll included
Key Exclusions
EVSE charging station equipment — owner-furnished, contractor-installed only
Generator and ATS — by owner's equipment vendor per E-500 series (install included if GC-directed)
Low-voltage data, telecom, AV, and security systems — by separate Division 27 contractor
HVAC controls and DDC wiring — by mechanical contractor per Division 23
◇ Silver
Scoped & Priced
Tight scope · Owner carries defined risk items · Lowest price
$458,900
Same base scope as Gold tier with the following scope modifications and risk reallocations. Silver is appropriate when the owner has reviewed and accepted the exclusion list below and is prepared to manage those risk items directly or through the GC.
  • All base electrical scope identical to Gold tier
  • Standard 1-year workmanship warranty
  • Weekly progress reports (email summary, no photo package)
Silver-Specific Exclusions (in addition to Gold exclusions)
Owner-directed change buffer excluded — all owner-directed changes priced as change orders
EV charging design-assist excluded — assumes current IEV-100 drawings are final, no design changes
Soil conditions assumed normal per geotech report — rock, contaminated soil, or dewatering are change order events
Existing utility relocation (if required by utility) — on utility's schedule, not contractor's
Line-Item Estimate — Gold Tier Basis Platt.com pricing · NECA units · PW included
# Description Qty Unit Unit Cost Material Labor Total
1Main service entrance — 2,000A switchboard, 480/277V 3Ø, Square D I-Line1LS$38,400$12,800$51,200
2480V panelboards (3 units) — MDP, DP-1, DP-23EA$4,200$12,600$5,400$18,000
3208/120V panelboards (4 units) — LP-1 through LP-44EA$2,800$11,200$4,800$16,000
4480V feeders — conduit and wire, MDP to sub-panels1,240LF$18.40$14,800$7,816$22,816
5Branch circuit wiring — 20A circuits, offices and exam rooms4,800LF$1.82$5,616$3,120$8,736
6EMT conduit — 1" to 4", above ceiling rough-in6,200LF$4.40$14,880$12,400$27,280
7Underground conduit — PVC Schedule 40, 4" service lateral280LF$6.20$1,736$5,040$6,776
8Interior LED lighting fixtures — offices, corridors, exam (per schedule)186EA$310$57,660$18,600$76,260
9Lighting controls — Lutron Vive wireless dimming + occupancy sensors1LS$18,400$6,200$24,600
10Emergency/exit lighting — battery backup units + exit signs42EA$280$8,400$3,360$11,760
11Fire alarm system — Notifier FACP, addressable, complete1LS$28,600$14,800$43,400
12Nurse call rough-in — Rauland Responder 5, conduit and wire1LS$4,200$6,800$11,000
13Site lighting — 14 LED pole fixtures, 30' poles, footings14EA$1,840$25,760$11,200$36,960
14EV charging rough-in — 24 circuits, 50A 240V each, panel capacity24CKT$680$8,640$7,680$16,320
15Devices — outlets, switches, data boxes (install only, devices by owner)320EA$12$3,840$6,400$10,240
16Grounding and bonding — complete per NEC Article 2501LS$2,800$3,200$6,000
17Temporary power — construction, per OSHA requirements1LS$1,200$2,400$3,600
18Permits and inspection fees — City of Olympia electrical1LS$4,800$1,200$6,000
19Prevailing wage burden — PW rate delta from open shop (per L&I)1LS$48,200$48,200
20Overhead and profit — 19.8% on direct costs1LS$75,752
GOLD TIER TOTAL BID $263,332 $182,216 $481,200
Bill of Materials — Major Items Platt.com April 2026
Item / Description Manufacturer / Model Qty Unit Unit Price Extended Source
Main switchboardSquare D Model 6 — 2,000A 480/277V 3Ø1EA$28,400$28,400Platt.com
480V panelboard — MDPSquare D NQ 400A MLO 42-circuit1EA$4,840$4,840Platt.com
208V panelboard — LP seriesSquare D QO 200A MLO 42-circuit4EA$2,180$8,720Platt.com
4" PVC Schedule 40 conduitCantex — 10' lengths28STK$84$2,352Platt.com
1" EMT conduitAllied — 10' lengths360STK$14.20$5,112Platt.com
12 AWG THHN wireSouthwire — 500' spools24SPL$142$3,408Platt.com
4/0 AWG XHHW feeder cableSouthwire — 500' reels6REL$1,840$11,040Platt.com
LED troffer 2×4 (office)Lithonia RT5 Series — 3500K 50W128EA$186$23,808Platt.com
LED downlight (exam rooms)Lithonia CPANL 4" 2700K medical grade58EA$224$12,992Platt.com
Occupancy sensorsLutron LXNCS-1PS — ceiling mount84EA$88$7,392Platt.com
Fire alarm panel — FACPHoneywell Notifier NFS2-30301EA$6,400$6,400Viking Supply
Addressable smoke detectorsNotifier FSP-951 — photo + thermal64EA$84$5,376Viking Supply
LED area light — siteLithonia DSXW2 LED 90W 5000K14EA$640$8,960Platt.com
Steel poles 30' direct burialValmont — 4" shaft, bronze finish14EA$680$9,520Graybar
50A 240V EV circuit breakersSquare D QO 50A 2-pole plug-in24EA$48$1,152Platt.com
Construction Schedule Matrix 21-week total duration · WA prevailing wage crew
Ph. Trade Scope Start Duration Milestone Crew / Notes
1Site underground — service lateral, site lighting conduit, EV conduit stub-outsWeek 13 weeksUnderground complete2 JW + 1 App · Coordinate with civil for trench opens
2Slab in-slab conduit — medical gas conduit, in-slab branch circuit conduitWeek 32 weeksPre-pour inspection2 JW · Coordinate with structural for slab pour schedule
3Gear installation — switchboard, MDP, LP-series panels, pull sectionsWeek 52 weeksGear setForeman + 2 JW · Requires permanent power from utility
4Above-ceiling rough-in — all EMT, junction boxes, fixture hangersWeek 66 weeksRough-in completeForeman + 4 JW + 2 App · Coordinate ceiling height with structural
5Feeder installation — all 480V and 208V feeders pulled and terminatedWeek 102 weeksFeeders energizedForeman + 3 JW · Requires switchboard set and utility service
6Fire alarm — FACP install, detector mounting, wiring, loop programmingWeek 123 weeksFire alarm testFA specialist + 1 JW · Coordinate with AHJ for pre-test walk
7Trim-out — fixtures, devices, cover plates, panel directory, labelingWeek 163 weeksTrim complete2 JW + 2 App · Coordinate with paint and flooring completions
8Testing, commissioning, and punchlist — all systems, load testing, lighting controlsWeek 192 weeksCertificate of occupancyForeman + 2 JW · All subs coordinate for CO inspection
Risk Register 6 items identified
HIGH
Utility service timing — Puget Sound Energy (PSE) lead time
PSE lead times for new 2,000A commercial services are currently running 14–18 weeks from application. If NTP is not issued and utility application filed within 2 weeks of award, the gear installation phase (Phase 3) will be delayed, pushing the entire schedule right.
→ Mitigation: File utility application within 72 hours of NTP. GC to expedite building permit to allow temporary power by Week 4.
MED
EV charging layout not finalized — scope clarification needed
Current IEV-100 drawings show 24 EV circuits but the owner has indicated the layout may change to accommodate accessible parking redistribution. Any change to the EV circuit count or panel sizing after permit application is a change order event.
→ Mitigation: Request written owner confirmation of final EV count before permit application. Platinum tier includes design-assist to resolve this prior to drawing submission.
MED
Nurse call system selection — Rauland vs. alternate
Specifications call for Rauland Responder 5 but owner is evaluating a competitive system. Rough-in conduit locations are identical; however, device types and wire counts differ. If owner changes system selection, a change order will be required for wire count adjustment.
→ Mitigation: Price rough-in only; confirm owner's final system selection before wire pull begins in Phase 4.
MED
Prevailing wage rate adjustment — L&I July 2026 update
WA L&I typically publishes updated prevailing wage rates in July. If project award occurs before July and construction extends past September, a portion of the work will fall under higher rates. Estimated exposure: $4,200–$8,400 depending on crew hours remaining at rate change date.
→ Mitigation: Escalation clause requested in subcontract. Platinum tier includes this contingency; Gold and Silver do not.
LOW
Material escalation — LED fixture lead times
Current Lithonia RT5 lead times are 6–8 weeks. Prices valid as of April 2026. This proposal is valid for 60 days. If award is delayed beyond June 30, fixture pricing may require updating.
→ Mitigation: Place fixture order at award regardless of NTP date to lock pricing and reserve allocation.
LOW
Existing utility stub location — pending as-built verification
Site plan shows existing 4" conduit stub from adjacent parcel. As-built location has not been field-verified. If stub is not in location shown, underground Phase 1 will require rerouting (est. $2,800–$6,400).
→ Mitigation: Pothole and verify stub location within 2 weeks of NTP before underground work begins.
Walk-Away Conditions This bid is withdrawn if any condition is triggered